First shot from the top of the hill looks towards the main line. Top centre you can make out the pile drivers and cranes. The route of the new line passes to the left just below the factories.
Here is evidence of the test boring
Looking down on the work site. Two very long permanent way trains were parked on the branch the whole time I was there. Rail replacement bus joy for some people I guess!
This is the access "road" to Wilbury Hill from the site
Work has also started on the farmer's accommodation underbridge. The field between the two embankments would have been completely cut off. There was also talk of it being used for access to the industrial area as currently the only way in is through residential areas constrained by the low arch railway bridge in Woolgrove Road.
Looking back at Wilbury Hill with the test boring in evidence. It will be interesting to compare this photo to one when the chalk removal has been completed.
Returning down the Stotfold Road a shot of the work site.