Sunday, 3 March 2013

Sunday March 3rd

I am afraid there is very little to report this week. The main changes are at the Hitchin North Junction end and mainly concern fencing and access works. It does appear as if a short length of contact wire has been added to the overhead since last week.
 Palisade fencing completed apart from a small gap since last week
 Looking north towards the viaduct.
 Now looking south.  Still some more fencing to go in and presumably a gate to allow access to the steps and walkway.
Better view of the new steps.

Not quite sure what this is for but the ducts have some pull through lines so maybe power or communications
Steps and walkway leading up to the new junction.
Drainage work has advanced but still not going anywhere as the wet patch on the pad shows.
Bit hard to make out but the contact wire has been added on this short run on to the new embankment section.