Tuesday 28 February 2012

Photos from 26th February

Not a lot of change this week. The two cranes have moved to the other side of the main line and are now located by the scrap yard. I can see now that one is a drilling machine doing some test drilling I am guessing.

Walked out along side the existing Cambridge branch and took this shot looking north towards the route of the new line.  The haul road runs alongside the orange fence in the middle of the picture.  This will eventually be an embankment.  You can just make out the access gate shown in last week's report centre left.
A new fence blocking this public footpath has been erected since my last visit.  No signs explaining why!  Picture taken over the fence towards the new office block.  The new line crosses the field in the foreground prior to joining the existing embankment.  I visited the site compound on another matter this week and the office block is actually a quite substantial two story affair.  The access from the road still hasn't been completed and there are temporary traffic lights in operation.
Here we can see the relocated drilling machine and crane.  I didn't go any further this week as there didn't appear to be much change.
Surface of the site seemed to have been further levelled and rolled.  The new concrete seen last week had been covered with hardcore.
On my way there I saw that the hole in the bridge had still not been repaired.  Maybe they were struggling to find some imperial blue bricks!  They should take advice from my friends at Broadway Station who seem to expert at locating and cleaning up blue bricks.  They are doing an amazing job re-constructing the station and platforms all with volunteer labour and the generous donations of local people and visitors.  You can follow their progress here at the Steaming to Broadway Blog.
http://broadwaygwsr.blogspot.com/

Sunday 19 February 2012

19th February

This week I noticed a fair bit of activity between the old Midland goods yard and the scrap yard in Cadwell lane.  Further tree clearance along the old Bedford line embankment had been carried out albeit only on the former trackbed rather than the embankment slopes.  This was presumably for access from the goods yard end.  Also more redundant track maintenance machines were removed by road from the goods yard latterly a Fastline Permanent Way Depot until the failure of the parent company Jarvis.  However at lunchtime on Thursday, disaster struck when a digger somehow managed to collide with the parapet wall of the Grove Road underbridge.   Brickwork was hanging over the road which resulted in three way temporary traffic lights and rush hour chaos.  The damaged brickwork has now been removed and a temporary site fence erected.  It was fortunate that no one was injured as a result.  My first photo shows the hole in the wall.
Looking towards the site compound where a substantial block of site offices has been installed.  Path of the new embankment is quite clearly defined now that the fields either side have been ploughed.  New access gates have also been erected since my last visit.
Looking towards the main line from the end of Wilbury Way, two cranes have appeared in the sewage treatment works along with some assorted plant.  In the foreground a water pipe is in the process of being connected and runs across the field to the haul road.

Embankment removal seems to have finished roughly in line with the northern edge of the scrapyard.  In the foreground is a new area of concrete presumably covering the gas main.  Apologies for the shadow!  Sun was very low at that time of the afternoon.
Site toilets have moved again!
Looking back towards the bridge by the scrapyard
A pile of scrap formed of what I guess is the remains of the diverted gas main
Same cranes from the other side of the main line
Looking back towards the scrapyard.  The surface where the machines are is now levelled and hardcore laid.

Sunday 12 February 2012

Update 11th February

Braved the snowy conditions and a very cold day to visit the Cadwell Lane end of the site.  Although it was very cold, supposedly -10C during the night, it was actually quite pleasant walking in the bright sunshine on the crisp snow.  The removal of the former Bedford line embankment had continued and is about halfway to the bridge by the scrapyard.  There is more heavy plant on site to do this than at my last visit and yet the progress is relatively slow.  I am sure that the Victorian navvies that built this had very little in the way of mechanised assistance.   The first photo shows the extent of the removal work.  The site toilets have been moved up to the site container.  Behind is a passing East Coast express still in its old GNER livery heading towards London.
The scrapyard is immediately to my right.  The gas main trench has now been filled in.

Looking back towards the scrapyard from further north.  The new permanent security fence has reached this spot now.  Immediately in front is the filled in gas main trench.
More spoil has been deposited on the triangle, some of it actually on the pegged out line of the new viaduct.
Turning around and looking back along the line of the removed embankment
Finally a shot from Bury Mead Road looking across the redundant part of the Anglian Water treatment works.  Yet another GNER liveried East Coast service is heading north.  The locomotive is passing the scrapyard behind the tall trees to the left.  You can quite clearly see the lower Bedford embankment below the passing train.  The extreme right of the photo is where the new line will leave the main line and start its climb up to the viaduct.

Tuesday 7 February 2012

Map of work site

Bad weather prevented me from visiting the site this weekend.  Six inches of snow didn't seem worth the risk!   I have created a Google map that shows the general work site area.  The pin pointers have location information and the photo pointers are locations where I have taken some of the pictures.  Despite spending some time I couldn't embed it so it opens in a new window.  Hope it helps give an overview of the various locations.  You can zoom in and see how it was before work started.  The Bedford branch is to the left of the main line embankment.  You can follow this back to the station and see how it accessed the former Midland Railway goods yard.  This would be the reason the line was double track all the way to Hitchin station so the Midland could access their own yard with needing to go onto Great Northern metals.  To the left of the goods yard you can see the row of cottages still known as Midland Cottages to this day, obviously built for Midland Railway workers.


Click here for a map of general work site area