Saturday, 19 January 2013

Wintery scene at the construction site

Managed to visit the site on a very snowy day.  There were a few changes to report.   At the Cadwell Lane end there was drainage work underway next to the River Hiz bridge.  At the end of Wilbury Way, there were lengths of welded rail visible on the embankment waiting for the visit of the track-layer in February.  They were delivered this week by train using the new Hitchin North Junction onto the 200m. or so of track laid on the link from the ECML and the start of the viaduct. They were then pulled around the chord by excavator.  The track-laying train is scheduled to visit over three days, Sunday 10th to Tuesday 12th February.  The work will be carried out mainly during the night so will try and get some shots if I can. There was no activity today whatsoever due to the weather.  Hope this does not continue and impact on the completion date.
First picture shows the new length of track laid laid on to the short length of embankment between the ECML and the viaduct.  Taken from Bury Mead Road looking across the Anglian Water STW.
 A closer look shows the ends of the sleepers more clearly.
 Frozen drainage work along side the embankment.

 Pump being used to remove water from the trench 
 Next to it a very large bore drainage pipe.
 Looking from the other side by the scrapyard entrance.
 Looking north from the same spot, more materials for the drainage work is stored next to the dumper. Guard rail work has been completed here since my last visit at the end of December.
 It looks as if some landscaping work has been recently carried out here at the end of the viaduct.
More drainage supplies here as well.  New scaffolding access has been installed.  This is the far side of the scrapyard.  Guard rail work not finished here.
Zooming out from the same spot.
 Looking across the bleak scene at the Bury Mead Springs conservation area.
 Looking south towards the scrapyard.  I am sure the dead tree has moved closer, maybe getting a better look!
 Wintery view through the viaduct to the new junction.
Turning right a view across the frozen waste that I struggled to navigate today because of the water/ice filled tracks left by a large vehicle that accessed the area through a new hole in the fence seen below.

 A First Hull train heads north about to pass under the viaduct.
 Here you can just make out two of the concrete pads used to support the crane.
A final winter scene shot of the viaduct.
 Looking from the end of Wilbury Way, lengths of rail await the track-laying machine.
This is the extent of the rail with the snow covered chalk quarry behind.  The machine that will be used is a New Track Construction Machine.  This runs on caterpillar tracks at the front guided by an operator.  It drops sleepers at regular intervals fed by a conveyor which is in turn supplied by a self powered gantry that brings sleepers from the rear of the train.  The laid out rail is drawn in to the machine and dropped onto the chairs.  The rest of the train then runs on the track it has just laid.  It is an incredibly fast and slick operation.  Hopefully I will get some shots and maybe a video of it in operation.

Sunday, 6 January 2013

First report of 2013

Again not a lot to report.  There was a considerable amount of activity along the former Bedford line embankment all week with machinery and construction workers moving back and forwards from the the former goods yard in Nightingale Road and the new Hitchin North Junction.  The work site and the west side of the main line has been scaled down considerably.  The site offices have gone and with them the generator that was always running.  There does not appear to be any access to the viaduct at this side now.  There still remain some guardrails to be installed here and on the link from the main line to the embankment.

 Site offices gone.  Guard rail still not installed along the walkway at this point.
 This is where the offices were located.  No guard rail at all here where the signalling equipment will be located.
Looking down from the higher ground.  Site is being tidied up.  I guess as soon as the weather permits they will landscape this area.
This shot was taken from the end of Wilbury Way.  Couple of new additions to the viaduct.  Not sure what they are for,  Apologies for the quality but the light was fading.
This shot shows the netting that has be added to the embankment this week along the whole length.
 Netting not quite reached the end.
 Permanent access staircase with security camera keeping an eye on the viaduct.
 I took this from the corner of the Centre Three car park.  This is the closest point to the new new embankment as it skirts around the end of the Wilbury Way industrial area.  There is a drainage ditch running along the edge of the car park.  The new culvert is just a bit too high at the moment to take the water from it.
 Looking to the right from the same spot, the embankment with its recently added netting heads towards the Cambridge branch.
 Finally a couple of closer shots of the quarry where the material for the embankment was taken

Sunday, 30 December 2012

29th December

All quiet today with absolutely nothing going on.  Very little to report as all the focus of the work over Christmas was inaccessible.  The next big development will be the track laying in February.  It is now just over 25 weeks to commissioning if all goes well.  However I did take two pictures while I was there.  First shows some concrete ramps that have been installed next to the embankment retaining wall.  I wonder if these will form part of  a permanent access to the viaduct for maintenence.

This shot shows the underside of the viaduct now that the scaffolding boards have been removed.  There are two drain pipes in this section which I am guessing will be connected to a drainage system which will take run off to the reed bed ponds nearby.

Wednesday, 26 December 2012

Boxing Day and work continues apace.

I managed to find a bit of time to visit the west side of the work site where the work to install the new Hitchin North junction has continued all over Christmas taking advantage of the shutdown.  There were a lot of construction workers in evidence and quite a lot of equipment stretching all the way along the embankment from the Grove Road bridge to the start of the viaduct.  It certainly looked as if the junction was in place.  Unfortunately there are no immediate vantage points from which to photograph.   I took a number from the back of the scrapyard and some from Bury Mead Road.  I will edit these and put them up tonight.  Family commitments require my presence now unfortunately!
This a shot of the finished link between the ECML and the viaduct.  The River Hiz was running quite high and I was only just able to get under the bridge.  The Bury Mead Springs area was very sodden which is not surprising really.
Not a great location to take a picture, this shows the general area of activity from the edge of the sewage treatment works.
Looking back from the Springs, a mobile crane lowers a length of rail onto the link.
 Two more shots of the same machine from the higher ground looking through the viaduct piers.
 Here it is moving another length of rail into position.
 Rail dropped into place guided by a colleague.
 I had wondered if was rail mounted but this shot shows it was running on caterpillar tracks.
 This picture was taken from Bury Mead Road across the sewage works. 
 Looking a bit closer, this certainly looks like newly laid track.
 This final shot shows workers standing on top of the River Hiz underbridge.  The guard rail that can just be made out behind the two workers on the left is on the Great Northern three arch side of the bridge in Cadwell Lane.  The more modest Midland Railway single arch is protected by scaffolding just visible bottom left.   By the time I left the crane was moving rail onto the viaduct itself.



Sunday, 16 December 2012

Sunday 16th and Wednesday 19th December

Today's very brief visit was a bit of an anticlimax after last Monday's site visit.  However there was something to report.   The ballasting of the viaduct had moved on to nearly the end.  The supported embankment between the viaduct and the mainline look a bit nearer completion.  During the week a lot of materials were moved on to the former Bedford embankment.  These were visible on the Grove Road bridge along with some temporary lighting, probably in advance of the Christmas shutdown.
First picture shows the link between the viaduct and the mainline. The edging is almost finished.
A digger can be seen on top of the ballast heap, possibly preparing the location of the new junction.
 From the same spot a shot of the viaduct.  The digger I saw on top on Monday has moved to the start of the final two sections.
 And the same digger from the far side of the scrapyard.  A large heap of ballast is to the right of the crane.  Two red hoppers which can be seen to the left are presumably used to move the ballast up on to the viaduct.
 The light started to fade when I took this shot next to the dead tree by the scrapyard.  The large blister is for a signal and the cabinet to hold the control equipment.  A gap has been left in the fencing to allow this to be installed.
 The light was too bad to take any more pictures after this one.  This shows one of the expansion gaps I mentioned in the previous report.  Whilst I was on the viaduct, I noticed four large concrete pads on the higher ground which were not visible from ground level..  These were put in to support the crane when lifting sections of viaduct into place.  These will be removed later when the site is tidied up.
 This will be the focus of the work over Christmas, the future location of Hitchin North Junction.   On Wednesday 19th, the work on the link seems to have moved on again with the scaffolding gone. 
 A closer look reveals the ballasting digger has moved on to the link.
And looking to the right, the rollers seen on the embankment during the ballasting work there are now here.  Just below the drainage pipe is the level of the former Bedford line.  This has been vital in moving materials and plant onto this area of the worksite.  This week has again seen a lot of machinery and workers moving along what was a double track width embankment.

Tuesday, 11 December 2012

Site visit part two

This is the continuation of yesterday's report of my visit to the site.

 Looking down on the ECML, a Grand Central service heads north.
 While a minute later another heads south.  You can just see orange clad workers to the right of the bend where the new line will leave the main line.
 Another view south from the viaduct.
 Looking back the other way.  The scaffolding halfway along is where we gained access to the viaduct.
 Here is one of the prepared "blisters" ready to accept the overhead gantry.
 Moving round parallel to the main line, ballasting hasn't reached here yet. The red crane right of centre is being used to pump concrete up onto the supported section of embankment.
 This shot is taken right from the end of the viaduct.  This is the short section of embankment linking the turnout from the main line to the viaduct.  It is retained by the wall seen in previous reports to minimise the size so as not to impact on the adjacent scrapyard. The concrete work here is being put in to keep a train in place in the (very unlikely) event of a derailment.
 This is the future location of Hitchin North junction which will go in during the Christmas possession of the main line.  Soon as this section is ready, sufficient track will be laid to allow the track laying machine to pull off the main line without causing any delay to scheduled services.  The concrete feed pipe is just in front of the construction workers.  Behind them you can clearly see the solum of the former Bedford line.  Further on by the bend, the new points are being made up in ready to be installed over Christmas.
I don't think we fully appreciate the amount of work carried out on our behalf at very unsocial hours by Network Rail.  Most of us tend to complain about the inconvenience it might cause us but a lot of workers won't be at home on Christmas Day or Boxing Day.
 Turning around, you can appreciate the gradient of the viaduct.  This last section is just cast concrete at present. Further on the blue waterproof coating is being added.  The dead tree next to the scrapyard that has featured in many previous pictures can be seen to the left with Bury Mead Springs behind.
 Looking down to the right, this is the bridge that carries the main line over the access road to this part of the construction site also seen in many other photos.
 Returning along the viaduct, we are now on the waterproofed section.
 Now we are on the section that has the matting that will protect the waterproofing from the ballast.  Every now and then there is drain that will take the water away to the reed beds.  Between the second and third pallets of slabs, you can just make out metal plates on the sides of the viaduct.  These are expansion joints that feature all the way round.
 Here you can see the end of the ballasted section.  The paving slabs that are stacked up are laid along the edge to help contain the ballast.
From this close up it appears that the ballast has a camber presumably to assist with the tight curve.  I didn't notice this at the time.



 Another look across the main line.
My final shot shows the conservation area where so many previous pictures have been taken from.  On the extreme right is the former Bedford line embankment as it heads towards Ickleford.  Again many thanks to Network Rail for the courtesy shown to me during the visit.